FOR IMMEDIATE RELEASE:

CONTACT:

Karl Bremer, Communications Specialist
VERSA-LOK Retaining Wall Systems
Phone: 651.770.3166
Email: kbremer@versa-lok.com
Web: www.versa-lok.com



VERSA-LOK Bronco is an attractive heavyweight time-saver for contractor

December 6, 2006

For contractor Arvid Jereczek, building a segmental retaining wall using traditional 82-pound VERSA-LOK units is child’s play. Building a wall with VERSA-LOK’s new 4,500-pound Bronco SRW system, however, presented a whole different challenge. But after completing his first Bronco wall, the Eau Claire, WI, contractor can’t wait to get started on his next one.

“I wish we would have had them about four years ago,” Jereczek enthused.

Jereczek’s company, American Express Transport, has installed a lot of segmental retaining walls. But they had never worked with blocks as large as Bronco until this project at a commercial office building parking lot came along.

“We probably would have gone with a regular segmental retaining wall like VERSA-LOK Standard or Mosaic,” says Jereczek. “There wasn’t a whole lot of (total installed) cost difference between the two products. The time savings was the biggest factor in going with Bronco.”

Bronco is installed much like any other SRW. Each unit weighs about 4,500 pounds and displays 14 square feet of face area with a four-panel, natural-stone relief appearance. Bronco units are made in four different face patterns. By alternating the four patterns, a random pattern can be achieved throughout the wall.

Bronco units are wet-cast using approximately 1.25 cubic yards of concrete per unit. Steel-cable pick rings are cast into the top and back of the unit for easy placement using appropriate lifting equipment. Alignment knobs molded into the top of units and channels molded into the bottom ensure correct near-vertical positioning and allow for tight, variable-bond construction. Cap units are designed to allow for landscaping to the face of the wall at the top.

Although Bronco units can be set on an 8-inch granular road-base leveling pad, Jereczek’s crew installed their wall on a “lean” concrete footing.

“The very first course is the hardest because you’re trying to get them exactly level. By using a concrete leveling pad, you put them down and you’re done,” says Jereczek. Once the base-course is in place, each one is leveled front to back and side to side with adjacent blocks and shimmed up if necessary.

Bronco units are placed using a backhoe and chain to hoist them. Once placed, they can easily be nudged into position with the backhoe bucket.

“We were figuring it would take us five minutes per block,” says Jereczek. “But it was even faster than that. We had one placed about every three minutes.”

Because Bronco can be built up to 10 feet tall without geogrid, it’s ideal for installations with site constraints. However, Jereczek says that wasn’t an issue on this project and had no bearing on choosing Bronco.

“It was the time savings. We saved at least a week-and-a-half” by using Bronco over a conventional SRW, he notes. The project was installed in October, so it was imperative that they have time on their side before the Wisconsin winter set in. “Plus, we wanted the random-pattern look that Bronco has.”

Two walls were built to create parking areas adjacent to the office building: one 135-foot wall and one 80-foot wall. The walls used 97 full Bronco units, six half units and 37 caps for a total wall surface of just over 2,000 square feet.

Jereczek was impressed with the quality of the Bronco units.

“They were totally uniform,” he remarked. That made installation all the more quicker. Once the wall was in place, he added, “We ran a ’dozer right up next to it and they didn’t move.”

Jereczek says they’ll stain the wall faces next spring. And he’s anxious to start on the next Bronco job.

“I hope to start a long relationship with these blocks,” Jereczek concludes.

   



ABOUT US
| WHAT ARE SRWS? | WHAT'S NEW | FOR THE MEDIA
CONTACT | LINKS | SITE MAP
ARCHITECT/ENGINEER | CONTRACTOR | HOMEOWNER
HOME